In building A, painting works are coming to an end in staircases B and C. In turn, in staircases A, B and C, the installation of wall panels at the entrance doors is in progress. The garage is being tidied up. Building B has successfully passed the inspection of the State Fire Service, thanks to which it will soon be possible to apply for an occupancy permit.
9/18/2024
HOUSING DEVELOPMENT NEWS - SEPTEMBER 2024
9/18/2024
HOUSING DEVELOPMENT NEWS - SEPTEMBER 2024
Building B is almost ready to welcome future residents, the final improvements are being made to the apartments. The installation of letter boxes in the stairwells has been completed. Thanks to numerous plantings, the estate is becoming even greener, the lawns and gardens in the ground-floor apartments have also become greener, and soon the planting will continue - soon new plants will appear at the back of building B. Some fencing panels have also been installed here and on the side of the railway siding.
8/27/2024
HOUSING DEVELOPMENT NEWS - AUGUST 2024
12
8/27/2024
HOUSING DEVELOPMENT NEWS - AUGUST 2024
Work in both buildings is ongoing. In building A, plaster is being laid on the staircases, while 2 staircases in building B are already prepared for painting, and one staircase is already painted. Parking spaces have already been painted in garage hall B. The ordered shrubs and grass have arrived at the estate and work on planting greenery has begun. Soon, greenery will appear on the garage ramp next to building A and on the road along the estate as well as at the entrances to the staircases. Work on fencing tenants' gardens is also progressing. Street lamps were also installed in the estate.
7/20/2024
HOUSING DEVELOPMENT NEWS - JULY 2024
5
7/20/2024
HOUSING DEVELOPMENT NEWS - JULY 2024
The tile facade of the first wall on the Winnica side of building B has been completed. Currently, work is underway on the facade of building A, including the wet facade. The floors in the small staircase of building B are already done, and the plastering in building A is being finished. Work is also being carried out on the roof of building B (small staircase), where the first layer of roofing felt has already been made. Styrofoam has been placed on the roof of building A and screeding is planned this week. The laying of Styrofoam begins on the roof of building B (large staircase). The installation of window joinery is nearing completion, and in the large staircase of building B, partition walls have been made on the ground, first and second floors, and currently masonry work is underway on the third floor.
15/5/2024
HOUSING DEVELOPMENT NEWS - MAY 2024
3
15/5/2024
HOUSING DEVELOPMENT NEWS - MAY 2024
Work on the investment is entering its final phase, and the access road to the estate is currently being constructed. Work is being carried out on internal communication routes. Tiles are being laid on the staircases.
11/4/2024
HOUSING DEVELOPMENT NEWS - APRIL 2024
5
11/4/2024
HOUSING DEVELOPMENT NEWS - APRIL 2024
Tiles are being laid in the staircases, and the installation of internal window sills in the apartments is in progress. Almost all balcony railings have been installed.
The installation of the entrance doors to the premises has begun.
Work on the rainwater installation in Marynin Street is in progress.
10/2/2024
HOUSING DEVELOPMENT NEWS - FEBRUARY 2024
6
10/2/2024
HOUSING DEVELOPMENT NEWS - FEBRUARY 2024
Building A
Scaffoldings are being removed from the facades, the floors on the balconies have been finished, acoustic insulation is being installed on the common areas and the walls and ceilings are being finished. Underfloor installations have been made in 40 premises, work will soon begin in the boiler room and drying of garages in order to finish the floors will begin. Building B
Only the finishing layer remains to be completed on the façade - all premises have underfloor installations and floors. The gas boiler room has been constructed and launched. The building is being dried out. The gas and electricity connections have been made, a transformer station has also been built on the investment site, and final works on the network in ul. Marinin
At the beginning of March, work will begin on removing smoke from the garage and installing elevators, followed by laying tiles in the common areas.
30/11/2023
HOUSING DEVELOPMENT NEWS - NOVEMBER 2023
1
1
30/11/2023
HOUSING DEVELOPMENT NEWS - NOVEMBER 2023
Building A
The façade is 70% complete, internal plastering is 30% complete, the electrical wiring in the apartments has been completed, and the common areas are already halfway done. The infiltration boxes responsible for the rainwater installation are already completed. PVC windows were installed just like aluminum windows in staircases.
Building B The façade is 65% complete, the internal plasters are 80% finished, the electrical installation in the apartments has been completed, and in the common areas it is approximately 70%. The installation of PVC windows in the building and aluminum windows in the staircases has been completed.
The installation of the transformer station and gas connection has started. The nearest one will have a sewage and water connection. The necessary equipment for the boiler room and radiators have been ordered.