• 2/18/2025

    NEWS FROM THE CONSTRUCTION OF THE ESTATE - FEBRUARY 2025

    In the L10 building, the construction of partition walls in the premises has been completed. Windows are currently being installed, electrical installations in the premises and sanitary installations are being carried out. The construction of the facade and roof insulation is being prepared. Reinforced concrete works of the ground zero level, i.e. the underground part of the building, are still being carried out in the L9 building. Within staircase A, the ceiling over floor -1 is being constructed, within staircase B, foundation works are being carried out, and within staircase C, reinforcement works on the joists and formwork of the ceiling over floor -1 are in progress. In the next month, reinforced concrete works will continue and masonry work will begin.

    • 1/20/2025

      NEWS FROM THE CONSTRUCTION OF THE ESTATE - JANUARY 2025

      The open shell of building L10 has been completed and 3 partition walls are being constructed. We plan to start installing windows in building L10 in the near future. Earthworks have been completed in the class B area of ​​building L9 and foundation work has begun there. Reinforced concrete works on the underground structure in the class A and C area of ​​building L9 are underway, i.e. the ceiling has been constructed over part of storey -2 and reinforcement works on the risers of storey -1 are being carried out.

    • 08/29/2024

      NEWS FROM THE CONSTRUCTION OF THE ESTATE - AUGUST 2024

      Earthworks are in progress. Preparation of the area for foundations and construction works is in progress.