NEWS FROM THE CONSTRUCTION OF THE ESTATE - FEBRUARY 2025
In the L10 building, the construction of partition walls in the premises has been completed. Windows are currently being installed, electrical installations in the premises and sanitary installations are being carried out. The construction of the facade and roof insulation is being prepared. Reinforced concrete works of the ground zero level, i.e. the underground part of the building, are still being carried out in the L9 building. Within staircase A, the ceiling over floor -1 is being constructed, within staircase B, foundation works are being carried out, and within staircase C, reinforcement works on the joists and formwork of the ceiling over floor -1 are in progress. In the next month, reinforced concrete works will continue and masonry work will begin.