HOUSING DEVELOPMENT NEWS - MAY 2025
Building A
Earthworks are underway. Part of the foundation slab has been completed. Implementation is progressing in stages, in accordance with the technological plan.
Building B
Works are underway related to the construction of the reinforced concrete structure of the fourth above-ground floor.
Building C
The implementation of the shell of the fourth above-ground floor has been completed. The construction of the reinforced concrete structure of the fifth above-ground floor has begun.