7/28/2025
HOUSING DEVELOPMENT NEWS - JULY 2025
The project is currently at an advanced stage of construction, with progress being made on the structure, masonry, joinery installation, and earthworks and foundations.
In Building C, on the 6th floor, work is underway on the construction of structural elements.
In Building B, in Section B1, the ceiling above the 5th floor has been completed, while in Section B2, the ceiling above the 5th floor is being installed.
Bricklaying work has been completed on the 5th floor of Building B.
In Building C, the construction of load-bearing walls has been completed on the 6th floor, while work on partition walls and infill walls is ongoing and progressing on the 4th floor.
Window installation has been completed up to the 2nd floor in both buildings B and C.
In building A, 60% of the foundation slab has been concreted.
Installation of the excavation protection system – Kopras – has been completed.