NEWS FROM THE CONSTRUCTION OF THE ESTATE - AUGUST 2025
Building Z5
Work on the construction of building Z5 has reached an advanced stage. All masonry work has been completed and the installation shafts have been fully constructed. The windows have also been installed. Further progress can be seen on the façade – a layer of adhesive and mesh has been applied to the north and west walls, while plastering has already been completed on the south wall. The balconies have been prepared for painting. Inside, plastering has been completed on the second floor, and plasterboard has been installed in the stairwells on the third, fourth, and fifth floors. The roof of the building has been covered with a full layer of roofing felt, and the wool insulation of the garage ceiling has been completed in full.
Building Z4
In building Z4, work on the partition walls has been completed, and installation shafts have been constructed up to the third floor. The installation of windows has also been completed. Insulation work has begun on the facade – polystyrene has been glued to the west and south walls. Inside, plastering has been completed on the third floor, and about half of the roof has been covered with roofing felt. Ninety percent of the garage ceiling insulation has been completed.