• 3/27/2025

    NEWS FROM THE CONSTRUCTION OF THE ESTATE - MARCH 2025

    Building Z5 – currently the ceiling and the second floor are available. After the reinforcement and formwork are complete, concrete works are underway, which have been introduced to the assembly of the floor wall.

    Building Z4 – in staircase 1, the construction of the second floor wall has been completed. At the same time, the bricklaying of the wall of the same floor in staircase 2 has begun.

    • 1/23/2025

      NEWS FROM THE CONSTRUCTION OF THE ESTATE - JANUARY 2025

      Work is underway on the construction of the ceiling over stair A in the Z4 building. At the same time, masonry works related to the construction of ground floor walls are being carried out in building Z4, in staircase B, and in building Z5. At the same time, internal electrical installations began. All works are carried out according to schedule.