• 8/30/2025

    NEWS FROM THE CONSTRUCTION OF THE ESTATE - AUGUST 2025

    Building Z5
    Work on the construction of building Z5 has reached an advanced stage. All masonry work has been completed and the installation shafts have been fully constructed. The windows have also been installed. Further progress can be seen on the façade – a layer of adhesive and mesh has been applied to the north and west walls, while plastering has already been completed on the south wall. The balconies have been prepared for painting. Inside, plastering has been completed on the second floor, and plasterboard has been installed in the stairwells on the third, fourth, and fifth floors. The roof of the building has been covered with a full layer of roofing felt, and the wool insulation of the garage ceiling has been completed in full.
    Building Z4
    In building Z4, work on the partition walls has been completed, and installation shafts have been constructed up to the third floor. The installation of windows has also been completed. Insulation work has begun on the facade – polystyrene has been glued to the west and south walls. Inside, plastering has been completed on the third floor, and about half of the roof has been covered with roofing felt. Ninety percent of the garage ceiling insulation has been completed.

    • 7/27/2025

      NEWS FROM THE CONSTRUCTION OF THE ESTATE - JULY 2025

      Building Z4
      Construction work is currently underway on the 6th floor of stairwell K1. At the same time, ceiling slabs are being laid above this floor. In stairwell K2, work on the ceiling is scheduled to be completed in week 30 of the year.

      Building Z5
      Building Z5 is currently in a closed shell condition. The bricklaying of chimneys and partition walls has been completed. Bricklaying work on installation shafts is currently underway. All windows have been installed on seven floors of the building. In addition, internal plastering work has already begun. The installation of scaffolding for facade work on the north and west sides has been completed.

    • 6/20/2025

      NEWS FROM THE CONSTRUCTION OF THE ESTATE - JUNE 2025

      Building Z4
      Construction work has reached the level of the ceilings above the 5th and 6th floors. Installation of window frames has been completed on the first floor, and is currently underway on the 1st floor. Work on masonry partition walls is being carried out on the 4th floor above ground. The progress of the works remains in full compliance with the investment schedule.

      Building Z5
      The open shell has been completed. Intensive assembly and finishing works are currently being carried out. Installation of window joinery is underway on the 4th floor, and parallel masonry of partition walls continues on the 7th, the last overground floor.

    • 5/12/2025

      NEWS FROM THE CONSTRUCTION OF THE ESTATE - MAY 2025

      On the K1 staircase of building Z4, the stage of bricklaying of external walls has been completed. Bricklaying work has moved to the next section – staircase K2, where construction of external walls has begun.

      On building Z5, bricklaying of external walls has begun on the sixth floor.

    • 3/27/2025

      NEWS FROM THE CONSTRUCTION OF THE ESTATE - MARCH 2025

      Building Z5 – currently the ceiling and the second floor are available. After the reinforcement and formwork are complete, concrete works are underway, which have been introduced to the assembly of the floor wall.

      Building Z4 – in staircase 1, the construction of the second floor wall has been completed. At the same time, the bricklaying of the wall of the same floor in staircase 2 has begun.

    • 1/23/2025

      NEWS FROM THE CONSTRUCTION OF THE ESTATE - JANUARY 2025

      Work is underway on the construction of the ceiling over stair A in the Z4 building. At the same time, masonry works related to the construction of ground floor walls are being carried out in building Z4, in staircase B, and in building Z5. At the same time, internal electrical installations began. All works are carried out according to schedule.