1/19/2025
NEWS FROM THE CONSTRUCTION OF THE ESTATE - JANUARY 2025
The ceiling above the garage has been laid and almost completely concreted. The first structural walls are rising from the side of Wiosny Ludów Street.
1/19/2025
The ceiling above the garage has been laid and almost completely concreted. The first structural walls are rising from the side of Wiosny Ludów Street.
12/10/2024
NEWS FROM THE CONSTRUCTION OF THE ESTATE - DECEMBER 2024
12/10/2024
Work is being completed on the external and contour walls of the garage hall. The last columns, pillars, for the ceiling over the garage are being reinforced. Formwork and reinforcement for the ceiling over the garage are being erected. Pouring of concrete for the floor over the garage hall will begin soon.
11/14/2024
NEWS FROM THE CONSTRUCTION OF THE ESTATE - NOVEMBER 2024
11/14/2024
Reinforcement works are being completed and garage floors are being poured. The installation of wall insulation and formwork for the reinforced concrete walls of the garage hall is being carried out.
10/17/2024
NEWS FROM THE CONSTRUCTION OF THE ESTATE - OCTOBER 2024
10/17/2024
The cornerstone has been laid for our latest investment: Kapitanat. This is an extraordinary moment full of emotions that heralds a new stage for the entire project! Currently, work on pouring the floors of the garage hall and reinforcement works are continuing.
9/12/2024
NEWS FROM THE CONSTRUCTION OF THE ESTATE - SEPTEMBER 2024
9/12/2024
Securing the excavation has been completed and piling for the foundation of the building is currently underway.
8/12/2024
NEWS FROM THE CONSTRUCTION OF THE ESTATE - AUGUST 2024
8/12/2024
Earthworks have started. Excavation for the garage hall is in progress.
7/14/2024
NEWS FROM THE CONSTRUCTION OF THE ESTATE - JULY 2024
7/14/2024
Ground strengthening has been completed. Concrete setting is in progress, excavation for the garage hall will begin in approximately 2 weeks.
6/12/2024
NEWS FROM THE CONSTRUCTION OF THE ESTATE - JUNE 2024
6/12/2024
Work is underway to prepare the platform for the piling machines. Work on securing the excavation for the underground garage will begin soon.
5/22/2024
NEWS FROM THE CONSTRUCTION OF THE ESTATE - MAY 2024
5/22/2024
Cleaning and archaeological works are underway. Earthworks are slowly starting.
Sebastian Szczypiorski
Kierownik Biura Obsługi Klienta
+48 783 830 799sebastian.szczypiorski@budlex.plSebastian Szczypiorski
Customer Service Office Manager
+48 783 830 799sebastian.szczypiorski@budlex.pl