Work progress
of our estates

Chosen investments list

Postęp prac na inwestycji Gajowa - lipiec 2025

Bydgoszcz

7/28/2025

Gajowa

The investment is at an advanced stage – construction and masonry work is underway in buildings B and C, joinery is being installed, the foundations in building A are being concreted, and the excavation has been secured.

Postęp prac budowlanych na osiedlu Enklawa 2 - budynki Z4 i Z5, lipiec 2025

Bydgoszcz

7/27/2025

Enklawa 2

The construction of the 6th floor ceiling is underway in building Z4. Internal plastering and preparations for facade work have begun in building Z5.

Postęp prac budowlanych na inwestycji Kapitanat w Gdańsku

Gdańsk

8/08/2025

Kapitanat

Piling and excavation work for the garage hall is underway on building A, while facade and interior finishing work is being carried out on building B.

Postęp prac na osiedlu Marynin - lipiec 2025

Warszawa

7/24/2025

Marynin

The investment has been completed, the facility has been approved for use, and the handover of apartments is proceeding according to schedule.

Postęp prac budowlanych na osiedlu Winnica w lipcu 2025

Toruń

7/17/2025

Winnica

In building L10, roofing, plastering, and facade work has been completed, and landscaping and preparations for flooring have begun. In building L9, the shell has been completed, partition walls are being finished, and installations and carpentry work are underway.

Postęp prac na osiedlu Urzecze w Bydgoszczy, Budlex

Bydgoszcz

17/2/2024

Urzecze 2

UDT acceptance of elevators is in progress. The apartments are already finished.

Postęp prac budowlanych inwestycji Vinea

Toruń

6/17/2025

Vinea

All construction and formal work related to the investment has been completed.

Postęp prac na osiedlu Jezioraj - czerwiec 2024

Olsztyn

7/27/2024

Jezioraj

Work on the estate is progressing according to the established schedule.

Postęp prac na budowie osiedla Enklawa w Bydgoszczy

Bydgoszcz

12/2/2024

Enklawa

Work is currently being completed on the ceiling over the garage in building Z4.

Libero - postęp prac na inwestycji w Olsztynie

Olsztyn

22.09.2022

Libero

The Libero development and the last 'B' building seen from a bird's eye view. We invite you to follow the progress of work on the site.

Osiedle Panorama w Olsztynie, postęp prac

Olsztyn

30.06.2023

Panorama

Insulation layers have been completed, soffits and canopies have been covered. The flashings have been completed and the external parapets have been fixed.